Projects / Footbridge / 2025

The Millrace Footbridge.

Client
Calder Weir Trust
Architect
Studio Ostrava
Our role
Structure and lifting
Completed
June 2025
The curved footbridge with pale steel ribs crossing a planted bank

The problem

A river 84 metres wide, no pier allowed in the water, and a weir upstream that could only be shut for a fortnight.

The answer

Two inclined steel arches tied through the deck, so the bridge pushes down on its abutments and never outwards. It was built on the bank in three pieces, each light enough for one crawler crane, and bolted together above the water at night.

We tuned the deck to stay out of step with walkers. A crowd crossing in rhythm moves it by less than the thickness of a coin.

84
metres clear, bank to bank
61
tonnes of steel, a fifth of it reclaimed
9
nights of river closure, of the 14 allowed

Load path

Where the weight goes.

84.0 m

5kN on every square metre

The deck is a shallow steel tray with a resin surface. It is designed for a crowd shoulder to shoulder, which is far heavier than it looks.

An engineer marking up a paper drawing with a pencil and a scale rule A site team in high-visibility jackets looking over a construction site

The client

“The bridge arrived in three pieces and was lifted in nine nights. Catenar drew the lifting sequence before they drew the bridge.”
Tobias Wren Tobias WrenProject lead, Calder Weir Trust

Embodied carbon

388kgCO₂e/m² of deck,
against our limit of 450